The Hills at Promontory – Course Construction Update
You’ve probably noticed that we’ve made significant progress on our new golf course, The Hills at Promontory. We’re excited to share an update and some “construction in-progress” photos with you! By the end of this week, 12 holes will be completed with sod while several others are in progress. Irrigation has been completed on all 18 holes, and roughly 40% of the cart path concrete has been poured. The Clubhouse footings have been poured and the foundation walls are starting to go up. We are so looking forward to adding these wonderful new amenities to Promontory next summer. Please stay tuned each week for a new update or spotlight on the course!